NATIONAL RIVER LINKING PROJECT

दैनिक समाचार

The National Perspective Plan (NPP) was prepared by the then Ministry of Irrigation (now Ministry of Jal Shakti) in August 1980 for water resources development through inter basin transfer of water, for transferring water from water surplus basins to water-deficit basins. Under the NPP, the National Water Development Agency (NWDA) has identified 30 links (16 under Peninsular Component & 14 under Himalayan Component) for preparation of Feasibility Reports. Details and status of the proposals for inter-state linking of rivers under the Inter Linking of Rivers Programme is furnished at Annexure.

   The implementation of the ILR projects depend on the consensus of the concerned States. Thus the interlinking of rivers programme is being pursued based on the principle of consensus and agreement among the concerned States. An interlinking project would reach the implementation stage once agreement amongst party states is reached on water sharing. Thereafter for implementation all requisite statutory clearances need to be obtained.

   Government of Uttar Pradesh has requested NWDA to take up the study of linking Sharda River to Gomtiriver. Draft Pre-Feasibility Report of the Intra State link viz; Sharda-Gomti link has been completed by NWDA  and submitted to the State Government in October, 2021.

   This Information was given by the Minister of State for Jal Shakti, Shri Bishweswar Tudu in a written  reply in Lok Sabha today.

AnnexurE

S. NoNameRiversStates concernedStatus
Peninsular Component   
1(a)Mahanadi (Manibhadra)– Godavari (Dowlaiswaram) linkMahanadiand GodavariJharkhand, Madhya Pradesh, Chhattisgarh, Telangana, Andhra Pradesh, Odisha, Karnataka and MaharashtraFR Completed.
1(b)Mahanadi (Bermul)– Godavari (Dowlaiswaram) linkMahanadi and GodavaridoFR Completed.* Preparation of DPR under progress.
2Godavari(Inchampall)-Krishna(Pulichintala) linkGodavariand KrishnaOdisha, Madhya Pradesh, Chhattisgarh, Telangana, Andhra Pradesh, Maharashtra and KarnatakaFR Completed.
3Godavari(Inchampalli)-Krishna (Nagarjunasagar) linkGodavariand Krishna–do–FR Completed.
DPR Completed.
4Godavari(Polavaram) – Krishna(Vijayawada) linkGodavari and Krishna–do–FR Completed.
5Krishna(Almatti) –Pennar linkKrishna and PennarTelangana, Andhra Pradesh,Maharashtra and KarnatakaFR Completed.
6Krishna (Srisailam)–Pennar linkKrishna and Pennar–do–FR Completed.
7Krishna(Nagarjunasagar)-Pennar (Somasila) linkKrishna and Pennar–do–FR Completed.
DPR Completed.
8Pennar (Somasila)–Cauvery(Grand Anicut) linkPennar and CauveryAndhra Pradesh, Karnataka, Tamil Nadu, Kerala and PuducherryFR Completed.
DPR Completed.
9Cauvery (Kattalai)–Vaigai–Gundar linkCauvery, Vaigai and GundarKarnataka, Tamil Nadu, Kerala and PuducherryDPR Completed.
10Ken–Betwa linkKen and BetwaUttar Pradesh and Madhya PradeshDPR (Phase – I, II & Comprehensive report) Completed.
Contd…
11 (i)Parbati – Kalisindh –Chambal linkParbati, Kalisindhand ChambalMadhya Pradesh,Uttar Pradesh and Rajasthan requested to be Consulted during consensus building)FR Completed.
(ii)Parbati-Kuno-Sindh linkParbati, Kuno and SindhMadhya Pradesh and RajasthanPFR completed.$
12Par-Tapi-Narmada linkPar, Tapi and NarmadaMaharashtra and GujaratDPR Completed.
 
13Damanganga – Pinjal linkDamanganga and Pinjal–do–DPR Completed.
 
14Bedti-Varada linkBedti and VaradaMaharashtra, Andhra Pradesh and KarnatakaPFR Completed. Draft DPR completed
15Netravati – Hemavati linkNetravati and HemavatiKarnataka, Tamil Nadu and KeralaPFR Completed.
16Pamba – Achankovil –Vaippar linkPamba,Achankovil and VaipparKerala and Tamil NaduFR Completed.
  $ Integration of Eastern Rajasthan Canal Project of Rajasthan and Parbati – Kalisindh – Chambal link.  
Himalayan Component 
1.Manas-Sankosh-Tista-Ganga(M-S-T-G)linkManas,Sankosh, Tista and GangaBHUTAN&INDIA (Assam,West Bengal and Bihar)FR completed. DPR in progress.
2.Kosi-Ghaghra linkKosi and GhaghraNEPAL&INDIA (Bihar and Uttar Pradesh)PFR completed
3.Gandak-Ganga linkGandak and Ganga–do–FR completed (Indian portion)
4.Ghaghra-Yamuna linkGhaghra and Yamuna–do–FR completed (Indian portion)
5.Sarda-Yamuna linkSarda and YamunaNEPAL&INDIA (Bihar, Uttar Pradesh, Uttarakhand, Haryana And Rajasthan)FR completed (Indian portion)
6.Yamuna-Rajasthan linkYamuna and SukriGujarat, Rajasthan, Haryana and UttarPradeshFR completed
7.Rajasthan-Sabarmati linkSabarmati–do–FR completed
8.Chunar-Sone Barrage linkGanga and SoneBihar and Uttar PradeshDraft FR completed
9.Sone Dam – Southern Tributaries of Ganga linkSone and BaduaBihar and JharkhandPFR completed
  Contd…
10.Ganga (Farakka)-Damodar- Subernarekha linkGanga, Damodar and SubernarekhaWest Bengal,Odisha and JharkhandFR completed DPR in progress
11.Subernarekha-Mahanadi linkSubernarekha and MahanadiWest Bengal and OdishaFR completed
12.Kosi-Mechi LinkKosi and MechiNEPAL & INDIA (Bihar and West Bengal)PFR completed
13.Ganga (Farakka)-Sunderbans linkGanga and IchhamatiWest BengalFR completed
14.Jogighopa-Tista-Farakkalink(Alternative to M-S-T-G)Manas,Tista and GangaAssam, Bihar andWest BengalDropped